Getta Byte SoftwareThe WBS and ScheduleTime to create a WBS for the the billing project.Hmm…What are the major tasks?We decided to purchase BillRite software.I know the milestones.• Finalize requirements• Purchase software• Customize software• Transfer data to cloud• Train personnel• Go liveI need to add detail or subtasks.Finalize Requirements• Gather requirements from users.• Gather requirements from customers.Purchase Software• Select vendor.• Negotiate contract.• Execute purchase.Customize Software• Define features.• Set up test environment.• Develop customization.• Test customization.Transfer data to cloud• Validate data.• Map fields.• Transfer data.Train Personnel• Develop training with vendor.• Schedule training for CSRs.• Conduct training.Go Live• Release system into production.Well! Let’s see what that looks like in a schedule.Getta Byte ScheduleWow! We have to get started so we can make the September 1 deadline.Getta Byte SoftwareThe EndAfter reviewing the Week 3 Lesson Video for Getta Byte Software, write and submit a one- to two-page paper on what Ima Payne, the project manager at Getta Byte Software, put together for her preliminary project schedule. Address the following questions.What types of information have we learned about the Getta Bill project by reviewing the project schedule and all the information used to generate it?If Ima made the decision to try to use the Agile Methodology for the Getta Bill project, what should she do?How could the WBS help the next step to plan using Agile?